That is curtailment, and it is the least understood profit center in mining. The same word also names the industry's supply story: grids ordering wind and solar farms to stop producing because the system cannot move or absorb their output, over 8 TWh of it in Texas alone in 2024. This guide covers the whole machine: both meanings of the word, the four ways a curtailed mining fleet gets paid, the real numbers from public filings, the rule changes landing between now and the end of 2026, what exists outside Texas, and what all of it looks like from a hosted customer's seat at our own sites.
The short answer
- Curtailment runs both directions: grids curtail generators (wind and solar switched off for lack of takers: 8+ TWh in ERCOT in 2024, 3.4 TWh in California) and curtail loads (big consumers paid to stop drawing power when the grid is stressed). Mining is the one industry built to profit from both.
- Miners are paid because they're fast: a fleet sheds full load in seconds with nothing broken and nothing lost but hashrate, which qualifies it for the grid's fastest, best-paying flexibility programs.
- The money is real and documented: one Texas miner booked roughly $71 million in credits in 2023, $56.7 million through the 2025 bear market, and $21 million in Q1 2026 alone, pulling its net power cost to 3.0 cents/kWh.
- For a hosted customer it's invisible by design: the site plays the curtailment game at fleet scale while your rate stays flat all-in; what you see is a brief, planned dip on the grid's worst hours, not a bill spike.
What Is Curtailment?

Texas already ran this experiment once. The CREZ transmission build-out, 3,600 miles of lines completed in 2013 for about $7 billion, cut wind curtailment from the mid-teens to nearly zero. A decade of renewable growth later, curtailment is back above 8 TWh. Wires alone don't stay ahead of generation; the grid also needs flexible demand that can live where the surplus is, which is precisely the niche mining filled.
Why Do Grids Pay Bitcoin Miners to Turn Off?

The Four Ways a Curtailed Fleet Gets Paid

| Lane | Trigger | Response needed | How it pays |
|---|---|---|---|
| Economic curtailment | Real-time price above mining breakeven | Your own decision, minutes | Power cost avoided, or power resold; ERCOT's own resource-adequacy modeling uses about $72/MWh as mining's switch-off point |
| 4CP avoidance | Highest 15-min grid interval, once per summer month | Predictive; sit out candidate peak afternoons | Next year's transmission charge shrinks; exposure runs roughly $50,000 to $67,000 per MW per year for a full-load site |
| Ancillary services | ERCOT dispatch or frequency signal | RRS ~30 s automatic; ECRS 10 min; Non-Spin 30 min | Capacity payments per enrolled MW plus performance payments per event; industry estimates for fully stacked programs run to $300,000 per MW-year at the high end |
| Emergency + contracted | Grid emergencies, storms, record peaks | Per agreement; ERS deployments | Contracted credits; the lane behind the largest single-month figures on record |
Two of these deserve a closer look. 4CP is the strangest and most consequential: ERCOT allocates transmission costs to large consumers based on their average draw during just four 15-minute intervals, the single highest of each summer month, measured after the fact. Miss the windows and a site's wires bill for the following twelve months collapses; run through them at full load and a 25 MW site can owe on the order of $1.25 million. Since nobody knows in advance which interval will be the monthly peak, miners curtail through dozens of candidate late afternoons each summer, and prediction quality is worth real money. Ancillary services invert the logic: the fleet is paid a capacity fee simply for standing ready, whether or not it is ever dispatched, with the fastest product (RRS, automatic response in roughly 30 seconds) paying the highest rates. Mining is one of the few load types that can qualify across the full product stack, and automation is the entry ticket.
What Is Curtailment Actually Worth? The Riot Record

Ready to Start Mining?
Free worldwide DDP shipping. Professional hosting from $0.055/kWh.
The Rules Are Changing: SB 6, 12CP, and the AI Squeeze
- Senate Bill 6 (signed June 2025) made flexibility a legal requirement. Transmission-voltage large loads interconnecting after December 31, 2025 must carry curtailment protocols allowing them to be shed during firm load shed, and ERCOT was directed to competitively procure demand reductions from customers drawing 75 MW or more. What miners volunteered to do, every giant new load will now be built to do.
- 4CP itself is under review. The same law requires the Public Utility Commission to finish reviewing the coincident-peak methodology and amend its rules by December 31, 2026, and ERCOT is openly rewriting how large loads connect and pay for transmission. Critics argue flexible loads dodge wires costs; one design on the table is a shift toward 12 coincident peaks, which would turn a four-window summer game into a year-round one. Whatever lands, the 2026 4CP season is likely the last under the old rules.
- The grid is growing into the flexibility it has. Texas broke its all-time demand record twice in two days in July 2026, peaking at a preliminary 91,308 MW, and ERCOT told regulators demand could roughly double within six years. At the same time, miners converting capacity to AI hosting are removing the very flexibility the system leans on, since AI workloads can't shed load the way hashrate can, and North American public miners alone held more than 5.1 GW of operational capacity in Texas as of Q1. Scarcer flexibility in a hungrier market points one direction: the megawatts that can still get out of the way should command more, not less.
Is Curtailment Only a Texas Thing?
- Canada: Alberta's energy-only market rewards curtailing straight off the price signal, including negative-price hours; Ontario and Quebec run capacity, peak-shaving and interruptible-tariff programs; industry mappings count a dozen distinct programs across Canada and ERCOT where a flexible miner rates a strong fit.
- Stranded and flared energy: the 151 billion cubic meters of gas flared globally in 2025 is curtailment's uglier cousin, and wellhead mining pioneered by operators like Crusoe turned billions of cubic feet of it into compute instead of flame. The same behind-the-meter model sits next to curtailed wind and solar, soaking up output the wires can't take.
- Hydro seasons: wet-season surpluses in markets like Paraguay and Ethiopia are seasonal curtailment by another name, and they're where a large share of new hydro-cooled mining capacity has landed. Our own take on how sites choose their power is covered in what a Bitcoin mining farm is and the sustainable mining breakdown.
How We Handle Curtailment at MillionMiner

| Hosted at a managed site | Home, retail or indexed plan | Own farm, in programs | |
|---|---|---|---|
| Who carries price spikes | The host; customer rate is flat all-in | You, in full; indexed plans spike with the market | You, hedged by your contracts |
| What an event looks like | Short planned dip on extreme hours | Bill spike, or a manual race to unplug | Dispatched or price-driven site response |
| Program access | At site scale, managed for you | None at single-machine scale | Full stack, if you build the automation |
| What it takes | A hosting contract | Luck with the weather | MW scale, market registration, staff |
Two practical notes complete the picture. First, if you're running at home on a wholesale-indexed plan in a volatile market, curtailment discipline isn't optional: the afternoons that pay sites millions are the same afternoons that can erase a home miner's month, and the home electricity math deserves a look before summer. Second, the surplus-energy thesis scales down: old, inefficient hardware that can't pay commercial rates still makes sense on genuinely cheap or stranded power, which is exactly the fit we flag on our legacy product pages. If you'd rather see the hosted version with your own machine, the free 24-hour miner test runs on our production floor, and the hosting cost breakdown shows where a flat rate comes from.
The Bottom Line
Frequently asked questions
A deliberate reduction of electricity that could have flowed: either generation curtailment, where grid operators order wind and solar plants to reduce output because transmission is congested or supply exceeds demand, or load curtailment, where large consumers reduce their draw in response to prices, programs, or dispatch instructions. Both are responses to the same mismatch of power, place, and time.
What is Bitcoin mining curtailment?
A mining operation deliberately reducing or shutting its load, either because real-time power prices exceed what the fleet earns mining, to avoid peak-window transmission charges, because it's enrolled in grid reserve programs, or under emergency agreements. The fleet loses only the hashrate for the window and is compensated through avoided costs, credits, or program payments.
Why does Texas pay Bitcoin miners to turn off?
Because flexibility is worth money to a grid that must balance in real time. ERCOT runs an isolated system with volatile prices, record-breaking demand, and huge renewable swings; a load that can hand back hundreds of megawatts in seconds is cheaper and faster than building equivalent peaker capacity. Miners are the largest load class that can do it, which is why federal energy statistics describe ERCOT's voluntary curtailment agreements as primarily crypto mining facilities.
How much money do miners make from curtailment?
The documented reference case is Riot Platforms: about $71 million in credits in 2023 including a single August with $31.7 million against $8.9 million of mined Bitcoin, $56.7 million through 2025, and $21 million in Q1 2026, which pulled its net power cost to 3.0 cents/kWh. Results scale with megawatts, market, and how many program lanes an operator stacks; industry estimates for fully stacked participation run to $300,000 per MW-year at the high end.
What is 4CP in ERCOT?
Four Coincident Peak: ERCOT allocates transmission costs to large consumers based on their average load during the four highest 15-minute grid intervals of the summer, one per month from June through September, identified after the fact. A site's behavior in those four windows sets its wires bill for the following twelve months, with exposure around $50,000 to $67,000 per MW per year. Miners forecast candidate peaks and curtail through dozens of summer afternoons to make sure they're offline for the four that count.
What are RRS, ECRS, and Non-Spin?
ERCOT's main reserve products, which loads can be paid to provide. Responsive Reserve Service (RRS) requires automatic response in roughly 30 seconds and pays the highest capacity rates; ERCOT Contingency Reserve Service (ECRS), added in 2023, requires response within 10 minutes; Non-Spinning Reserve allows 30 minutes and is the easiest entry tier. Participants earn capacity payments for standing ready plus performance payments when dispatched, and fast-curtailing mining fleets can qualify across the stack.
Doesn't curtailment hurt Bitcoin production?
Less than intuition suggests, because the hours worth curtailing are few and extreme. The events cluster into a handful of peak afternoons and emergencies; the reference August saw a miner cut more than 95% of load during those peaks and still produce 333 BTC across the month. The economics decide it: when an hour's power is worth more than the Bitcoin it would mine, producing through it is the losing move.
What is Texas Senate Bill 6 and what changes in 2026?
SB 6, signed in June 2025, requires large transmission-voltage loads connecting after December 31, 2025 to have curtailment protocols so they can be shed in emergencies, directs ERCOT to competitively procure demand reductions from customers of 75 MW and up, and orders the Public Utility Commission to finish reviewing the 4CP transmission-cost methodology by December 31, 2026. A shift toward a 12-peak design is on the table, which would spread the peak-avoidance game across the whole year.
Does curtailment exist outside Texas?
Yes, wherever power is stranded, seasonal, or volatile. Alberta's market rewards curtailing off the price signal directly, Ontario and Quebec run capacity and interruptible-tariff programs, Great Britain curtails over a tenth of its wind, and behind-the-meter mining monetizes flared gas and hydro wet-season surpluses that never touch a program at all. Texas is simply the deepest and best-documented market.
Does curtailment affect me as a MillionMiner hosting customer?
Operationally, barely; financially, in your favor. Our customers pay a flat all-in rate, so power-price spikes stay on our side of the contract, and our US sites run their own substations with uptime managed to a 99.9% target. What a customer sees during a grid event is a brief, planned dip in hashrate on the year's most extreme hours, which are precisely the hours when mining through the price would have cost more than it earned.
Can a home miner get paid to curtail?
Not directly in most markets: ERCOT's load programs operate at facility scale with registration, telemetry, and response requirements a single machine can't meet, though aggregators are beginning to bundle small loads in some regions. What a home miner can do is run the economic-curtailment logic manually, especially on wholesale-indexed plans where a few spike afternoons can erase a month's margin. At machine-count scale, that discipline is a big part of what hosting buys.
Bitcoin Miner (BTC)
Dogecoin / Litecoin Miner (DOGE, LTC)
Zcash Miner (ZEC)
Kaspa Miner (KAS)
Ethereum Classic Miner (ETC)
Siacoin Miner (SC)
Monero Miner (XMR)
Other Asic Miners
Hydro Miners
Lottery Miners
Mining Containers
Racks & Cabinets
Hydro Radiators
GPU & Graphic Cards
AI Server
Storage